Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

DonViejo

(60,536 posts)
Tue Oct 24, 2017, 08:18 AM Oct 2017

$300m Puerto Rico Recovery Contract Awarded to Tiny Utility Company Linked to Major Trump Donor

Source: The Daily Beast




A tiny utility company linked to a prominent Trump campaign donor has been awarded the massive contract to help rebuild the crippled island.

KEN KLIPPENSTEIN
10.24.17 7:29 AM ET

Puerto Rico has agreed to pay a reported $300 million for the restoration of its power grid to a tiny utility company that is primarily financed by a private-equity firm founded and run by a man who contributed large sums of money to President Trump, an investigation conducted by The Daily Beast has found.

Whitefish Energy Holdings, which had a reported staff of only two full-time employees when Hurricane Maria touched down, appears ill-equipped to handle the daunting task of restoring electricity to Puerto Rico’s more than 3 million residents.

Much larger utilities are more commonly used following natural disasters on the scale of Hurricane Maria, which devastated the island last month.

The private-equity firm that finances Whitefish, HBC Investments, was founded by Joe Colonnetta, who serves as its general partner.

Read more: https://www.thedailybeast.com/dollar300m-puerto-rico-recovery-contract-awarded-to-tiny-utility-company-linked-to-major-trump-donor

44 replies = new reply since forum marked as read
Highlight: NoneDon't highlight anything 5 newestHighlight 5 most recent replies
$300m Puerto Rico Recovery Contract Awarded to Tiny Utility Company Linked to Major Trump Donor (Original Post) DonViejo Oct 2017 OP
Gee. What can possibly go wrong? joshdawg Oct 2017 #1
How unexpectedly nice that a major project is awarded to a small company from Montana irisblue Oct 2017 #2
Sure enough. dalton99a Oct 2017 #3
Damn. I cannot believe the blatant corruption of this bunch. Laurian Oct 2017 #4
Trump needs to be in jail for this. SunSeeker Oct 2017 #5
At least 4000 dead imho Not Ruth Oct 2017 #7
The whole fascist party needs to go to jail elmac Oct 2017 #31
So what about all the other Turbineguy Oct 2017 #6
With two full time employees they'll have that entire island up and running in no time.... Bengus81 Oct 2017 #8
how much will the kick back be? mopinko Oct 2017 #16
This is TERRIBLE for Puerto Rico. This company isn't going to be Hortensis Oct 2017 #9
I don't believe that they have the right to vote for president Angry Dragon Oct 2017 #14
In Party primaries only. eom DonViejo Oct 2017 #23
They can vote if they have a permanent address on the mainland SCantiGOP Oct 2017 #27
. . . and plenty are moving and/or have already moved to the mainland. ATL Ebony Oct 2017 #36
Quid Pro Quo B Stieg Oct 2017 #10
So much for draining the swamp. LonePirate Oct 2017 #11
A photo of their project managers...not a joke. zaj Oct 2017 #12
From the article Botany Oct 2017 #13
What's wrong with our system of government that we janterry Oct 2017 #15
Puerto Rico should give the contract to Elon Not Ruth Oct 2017 #17
What?!? Tracer Oct 2017 #18
They were hired by PREPA TexasBushwhacker Oct 2017 #44
The efficient free market party is against competitive bidding IronLionZion Oct 2017 #19
Oh, that's what that was about. mahatmakanejeeves Oct 2017 #20
Trump merely took a hint from Dick Cheney DFW Oct 2017 #21
Grifters gotta grift! FSogol Oct 2017 #22
After a long hard day of thievery, corruption, and racketeering ... it Mueller Time Snake Plissken Oct 2017 #24
Small Montana firm lands Puerto Rico's biggest contract to get the power back on mahatmakanejeeves Oct 2017 #25
This contract will balloon with a lot of cost overruns. kimbutgar Oct 2017 #26
A House Committee with oversight of PR bankruptcy says it is concerned about deal. mahatmakanejeeves Oct 2017 #29
Of course, they don't have the manpower nor experience -- the job is over their head. ATL Ebony Oct 2017 #34
How this can happen astounds me. Where are our journalists, our news organizations looking out c-rational Oct 2017 #28
Small Montana firm lands Puerto Rico's biggest contract to get the power back on mahatmakanejeeves Oct 2017 #30
Thank you for the links mahatmakanejeeves. I should have said why does not MSM beat this drum, c-rational Oct 2017 #32
Here we go again. mahatmakanejeeves Oct 2017 #37
PR is over a barrel and basically needs the job done ATL Ebony Oct 2017 #33
Here we go not fooled Oct 2017 #35
Trump kept going on about the power grid there JI7 Oct 2017 #38
Oh for fux sakes! pandr32 Oct 2017 #39
Graft and coruption is SOP in Trump world Yo_Mama_Been_Loggin Oct 2017 #40
This contract was awarded by PREPA onenote Oct 2017 #41
I knew from the beginning that contracts were going to be awarded to his donors and buddies. niyad Oct 2017 #42
Corruption by Trump. Remember Iraq bs. rockfordfile Oct 2017 #43

irisblue

(32,980 posts)
2. How unexpectedly nice that a major project is awarded to a small company from Montana
Tue Oct 24, 2017, 08:24 AM
Oct 2017

Off to research now.

Laurian

(2,593 posts)
4. Damn. I cannot believe the blatant corruption of this bunch.
Tue Oct 24, 2017, 08:25 AM
Oct 2017

They just continue to abuse their power and are never held accountable.

So disheartening.

SunSeeker

(51,571 posts)
5. Trump needs to be in jail for this.
Tue Oct 24, 2017, 08:25 AM
Oct 2017

The blood of Puerto Ricans who died due to lack of electricity are on his kleptocratic hands.

 

elmac

(4,642 posts)
31. The whole fascist party needs to go to jail
Tue Oct 24, 2017, 11:00 AM
Oct 2017

RICO RICO RICO Racketeer Influenced and Corrupt Organizations Act

Turbineguy

(37,341 posts)
6. So what about all the other
Tue Oct 24, 2017, 08:29 AM
Oct 2017

dolts who contributed and voted for trump. Do they get a place at the trough or just empty promises?

Bengus81

(6,931 posts)
8. With two full time employees they'll have that entire island up and running in no time....
Tue Oct 24, 2017, 08:35 AM
Oct 2017

How much you getting from these people next time around Trump?? Nothing but middle men to point the electric utility on PR to the problem and say go fix that. This is No different than an Oil company like Halliburton getting contracts to build military housing and prisons in Iraq. BILLIONS of $$$ in tax payer money handed out to make rich men richer.

There needs to be one HELL of an investigation into this graft.

Hortensis

(58,785 posts)
9. This is TERRIBLE for Puerto Rico. This company isn't going to be
Tue Oct 24, 2017, 08:50 AM
Oct 2017

able to do the job adequately. Those poor people. They voted overwhelmingly Democratic and against Rump and so don't deserve this. All of us who didn't vote the Democratic ticket own all this. What a shame they can't share the misery.

Well, as this miserable and despicable handling drags out toward 2018, perhaps at least some of it will penetrate the right wing news bubble, and maybe even shame some of those culpable on the left.

SCantiGOP

(13,871 posts)
27. They can vote if they have a permanent address on the mainland
Tue Oct 24, 2017, 10:44 AM
Oct 2017

And thousands are now relocating to Florida.
Louisiana was a leaning Democratic State until Katrina caused the permanent relocation of thousands of mainly minority voters from New Olreans to Texas. This same effect may lock in Florida to the Dem column.

ATL Ebony

(1,097 posts)
36. . . . and plenty are moving and/or have already moved to the mainland.
Tue Oct 24, 2017, 11:46 AM
Oct 2017

There should be hell to pay for this.

Botany

(70,516 posts)
13. From the article
Tue Oct 24, 2017, 09:01 AM
Oct 2017

On Monday, The Washington Post reported that Whitefish Chief Executive Officer Andy
Techmanski is friends with Trump administration Interior Secretary Ryan Zinke. Moreover,
Whitefish is located in Zinke’s hometown of Whitefish, Monatana.


*****

2 employees?

 

janterry

(4,429 posts)
15. What's wrong with our system of government that we
Tue Oct 24, 2017, 09:07 AM
Oct 2017

have no check on this kind of corruption?

We can blame trump and his comrades as much as we want. But it's clear that our system has too few checks on abuse.

Tracer

(2,769 posts)
18. What?!?
Tue Oct 24, 2017, 09:33 AM
Oct 2017

Puerto Rico AGREED to hired this 3-man company?!?

What do they mean by "Puerto Rico"? Who did this? The Governor of PR?

What could possibly go wrong (or right).

TexasBushwhacker

(20,196 posts)
44. They were hired by PREPA
Wed Oct 25, 2017, 01:34 AM
Oct 2017

Here's an article from WP.

https://www.washingtonpost.com/national/small-montana-firm-lands-puerto-ricos-biggest-contract-to-get-the-power-back-on/2017/10/23/31cccc3e-b4d6-11e7-9e58-e6288544af98_story.html?utm_term=.e3476ed3d72a

"PREPA’s executive director, Ricardo Ramos, and a spokesman did not respond to emails asking why the utility didn’t activate the mutual-aid network. On a tour of the idled Palo Seco power plant, Ramos told reporters that Whitefish was the first company “available to arrive and they were the ones that first accepted terms and conditions for PREPA.”

Ramos said that the utility is “completely content” with the work Whitefish is doing. “The doubts that have been raised about Whitefish, from my point of view, are completely unfounded,” he added, saying that concerns about Whitefish were probably spread by jealous competitors.

Whitefish officials have said that the company’s expertise in mountainous areas makes it well suited for the work and that it jumped at the chance when other firms were hesitating over concerns about payment."

I read elsewhere that one contender asked for $25 Million up front. That seems reasonable considering the scope of the project, but that may have been a road block for PREPA.

IronLionZion

(45,450 posts)
19. The efficient free market party is against competitive bidding
Tue Oct 24, 2017, 09:48 AM
Oct 2017

why hire the best company for the job at the best price when you can just give sweetheart deals to your cronies? After all, it's the taxpayers' money, not Trump's.

mahatmakanejeeves

(57,488 posts)
20. Oh, that's what that was about.
Tue Oct 24, 2017, 09:50 AM
Oct 2017

I saw the article in the Flathead Beacon about the award of the contract, but there was no mention of who was behind it. Now I get it.

Whitefish Company Tapped to Rebuild Puerto Rico Power Grid

Two-year-old company brokered $300 million contract with island’s electric utility

BY TRISTAN SCOTT // OCT 21, 2017

A Whitefish-based energy outfit is playing a key role in restoring power on the hurricane-ravaged island of Puerto Rico, a windfall for the relatively untested Montana company, whose CEO said it is well-equipped for such a massive undertaking in the rural and rugged region.

Officials with Whitefish Energy Holdings say the company’s experience and expertise working in the Mountain West, and CEO Andy Techmanski’s 20 years rebuilding transmission lines here, furnishes crews with a skillset uniquely tailored to meet the challenges of repairing and reconstructing electrical transmission infrastructure on the island’s mountainous terrain, which Hurricane Maria rolled across last month, killing at least 49 people and leaving the majority of the island without power and in the dark.

Last month, the company signed a $300 million contract with the Puerto Rico Electric Power Authority (PREPA) to repair and rebuild 100 miles of transmission lines on the western portion of the island, and hopes to start turning some of the lights back on in the coming days.
....

Formed in 2015 by Techmanski, Whitefish Energy began eying the former site of the Columbia Falls Aluminum Company as a potential campus to build a transformer manufacturing plant, in partnership with Brazil-based Comtrafo S.A., a leading transformer manufacturing firm. At the time, Techmanski estimated the company would need to generate $15 million to $20 million in backorders with regional utilities in order to justify the manufacturing center, which so far has not panned out.

There was this comment:

DFW

(54,403 posts)
21. Trump merely took a hint from Dick Cheney
Tue Oct 24, 2017, 10:05 AM
Oct 2017

Cheney's Halliburton got just numbers of contracts from the Federal Government and the military for projects in Iraq, many of them contracts they never even had to compete for. And the Republican-controlled Congress never said a word. Halliburton's stock--of which Cheney had 200,000 $1 per share options at $19--went from $19 to $87 in a very short time, and SOMEBODY had to pay for the upkeep on his house on Kish. Anyone know how much is 200,000 X ($87-19-1)? Try $13,400,000. And that's just this one transaction.

Trump saw Cheney never had to answer for his corruption, so he figures (probably correctly) that he won't, either. Trump is right about one thing: he could shoot someone dead on Fifth Avenue in broad daylight and he wouldn't lose a vote. I would add to that--he wouldn't lose a day of freedom, either, as long as Sessions is Attorney General. Sessions would probably have the guy Trump murdered charged posthumously for assault, and then suspend the sentence, provided the guy didn't rise from his grave.

mahatmakanejeeves

(57,488 posts)
25. Small Montana firm lands Puerto Rico's biggest contract to get the power back on
Tue Oct 24, 2017, 10:24 AM
Oct 2017

Hat tip, edhopper: WP; Small Montana firm lands Puerto Ricos biggest contract to get the power back on

Small Montana firm lands Puerto Rico’s biggest contract to get the power back on

By Steven Mufson, Jack Gillum, Aaron C. Davis and Arelis R. Hernández October 23 at 9:29 PM

For the sprawling effort to restore Puerto Rico’s crippled electrical grid, the territory’s state-owned utility has turned to a two-year-old company from Montana that had just two full-time employees on the day Hurricane Maria made landfall. ... The company, Whitefish Energy, said last week that it had signed a $300 million contract with the Puerto Rico Electric Power Authority to repair and reconstruct large portions of the island’s electrical infrastructure. The contract is the biggest yet issued in the troubled relief effort. .... The unusual decision to instead hire a tiny for-profit company is drawing scrutiny from Congress and comes amid concerns about bankrupt Puerto Rico’s spending as it seeks to provide relief to its 3.4 million residents, the great majority of whom remain without power a month after the storm.
....

Whitefish Energy is based in Whitefish, Mont., the home town of Interior Secretary Ryan Zinke. Its chief executive, Andy Techmanski, and Zinke acknowledge knowing one another — but only, Zinke’s office said in an email, because Whitefish is a small town where “everybody knows everybody.” One of Zinke’s sons “joined a friend who worked a summer job” at one of Techmanski’s construction sites, the email said. Whitefish said he worked as a “flagger.” ... Zinke’s office said he had no role in Whitefish securing the contract for work in Puerto Rico. Techmanski also said Zinke was not involved. ... Techmanski said in an interview that the contract emerged from discussions between his company and the utility rather than from a formal bidding process. He said he had been in contact with the utility two weeks before Maria “discussing the ‘what if’ scenarios” of hurricane recovery. In the days after the hurricane, he said, “it started to make sense that there was a need here for our services and others.” ... On Thursday, Techmanski told CNN simply: “We called each ­other.” ... The scale of the disaster in Puerto Rico is far larger than anything Whitefish has handled. The company has won two contracts from the Energy Department, including $172,000 to replace a metal pole structure and splice in three miles of new conductor and overhead ground wire in Arizona.
....

The House Committee on Natural Resources is examining Whitefish’s role in Puerto Rico, said Parish Braden, a spokesman for the committee. The hiring of the little-known company has been noted by the trade publications Utility Dive and E&E News. ... “The size and unknown details of this contract raises numerous questions,” Braden said. “This is one of many things the committee is taking a close look at as it continues to work with the resident commissioner, governor’s office, and oversight board to ensure Puerto Rico’s recovery is robust, effective and sustained.”
....

Under the contract, the hourly rate was set at $330 for a site supervisor, and at $227.88 for a “journeyman lineman.” The cost for subcontractors, which make up the bulk of Whitefish’s workforce, is $462 per hour for a supervisor and $319.04 for a lineman. Whitefish also charges nightly accommodation fees of $332 per worker and almost $80 per day for food.
....

Hernández reported from San Juan, Puerto Rico.

Steven Mufson covers energy and other financial matters. Since joining The Post, he has covered the White House, China, economic policy and diplomacy. Follow @StevenMufson. Follow @StevenMufson

Jack Gillum is a reporter on the investigative team at The Washington Post. Follow @jackgillum

Aaron Davis is a reporter for The Post’s Investigative team. Follow @byaaroncdavis

Arelis Hernández covers Prince George’s County as part of The Washington Post's local staff. Follow @arelisrhdz

mahatmakanejeeves

(57,488 posts)
29. A House Committee with oversight of PR bankruptcy says it is concerned about deal.
Tue Oct 24, 2017, 10:51 AM
Oct 2017
A House Committee with oversight of PR bankruptcy says it is concerned about deal. Lawmakers may be more concerned when they price tag:


c-rational

(2,593 posts)
28. How this can happen astounds me. Where are our journalists, our news organizations looking out
Tue Oct 24, 2017, 10:45 AM
Oct 2017

for the people.

mahatmakanejeeves

(57,488 posts)
30. Small Montana firm lands Puerto Rico's biggest contract to get the power back on
Tue Oct 24, 2017, 10:55 AM
Oct 2017
Small Montana firm lands Puerto Rico’s biggest contract to get the power back on

By Steven Mufson, Jack Gillum, Aaron C. Davis and Arelis R. Hernández October 23 at 9:29 PM

....
The House Committee on Natural Resources is examining Whitefish’s role in Puerto Rico, said Parish Braden, a spokesman for the committee. The hiring of the little-known company has been noted by the trade publications Utility Dive and E&E News.
....

Hernández reported from San Juan, Puerto Rico.

Steven Mufson covers energy and other financial matters. Since joining The Post, he has covered the White House, China, economic policy and diplomacy. Follow @StevenMufson. Follow @StevenMufson

Jack Gillum is a reporter on the investigative team at The Washington Post. Follow @jackgillum

Aaron Davis is a reporter for The Post’s Investigative team. Follow @byaaroncdavis

Arelis Hernández covers Prince George’s County as part of The Washington Post's local staff. Follow @arelisrhdz

c-rational

(2,593 posts)
32. Thank you for the links mahatmakanejeeves. I should have said why does not MSM beat this drum,
Tue Oct 24, 2017, 11:10 AM
Oct 2017

but I fear the why. They are bought and complicit with exceptions like Rachael and Lawrence. Is there not a law which makes it illegal to use the public airwaves against the good of the country.

mahatmakanejeeves

(57,488 posts)
37. Here we go again.
Tue Oct 24, 2017, 11:46 AM
Oct 2017


Also, I have not had cable TV since 1986, so I can't be sure. The people you mentioned appear on cable or satellite TV, do they not? Neither service is regulated by the FCC, which oversees broadcast TV.

Finally, I believe the Washington Post is regarded as mainstream media. In its market, the Flathead Beacon is also a member of the mainstream media.

Welcome to DU.

ATL Ebony

(1,097 posts)
33. PR is over a barrel and basically needs the job done
Tue Oct 24, 2017, 11:27 AM
Oct 2017

By selecting what is probably the most ill-equipped company in the country shows how abhorrent 45 really is to find the least qualified for this massive project (2 people TOTAL, really??) and PR is on the hook for $300M. Hopefully another company can step up to prevent this travesty.

not fooled

(5,801 posts)
35. Here we go
Tue Oct 24, 2017, 11:31 AM
Oct 2017

Halliburton/KBR redux.

From the WaPo article:

Under the contract, the hourly rate was set at $330 for a site supervisor, and at $227.88 for a “journeyman lineman.” The cost for subcontractors, which make up the bulk of Whitefish’s workforce, is $462 per hour for a supervisor and $319.04 for a lineman. Whitefish also charges nightly accommodation fees of $332 per worker and almost $80 per day for food.







Same shit, different assholes.

pandr32

(11,588 posts)
39. Oh for fux sakes!
Tue Oct 24, 2017, 12:55 PM
Oct 2017

Only two full-time employees? Big Trump donor? Can we hurry up and march the deranged orange clown off to the guardhouse soon? People are dying and the U.S. is being ravaged and pillaged! Hurry up Congress!

niyad

(113,336 posts)
42. I knew from the beginning that contracts were going to be awarded to his donors and buddies.
Tue Oct 24, 2017, 04:36 PM
Oct 2017

couldn't they at least PRETEND to do the correct thing?