Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

bananas

(27,509 posts)
Fri Mar 7, 2014, 03:30 AM Mar 2014

United States puts MOX Fuel Fabrication Facility on cold standby

http://fissilematerials.org/blog/2014/03/united_states_puts_mox_fu.html

United States puts MOX Fuel Fabrication Facility on cold standby
By Pavel Podvig on March 5, 2014

The FY2015 budget proposal released by the U.S. administration, will effectively terminate the construction of the MOX Fuel Fabrication Facility (MFFF) in Savannah River:

Following a year-long review of the plutonium disposition program, the Budget provides funding to place the Mixed Oxide (MOX) Fuel Fabrication Facility in South Carolina into cold-standby. NNSA is evaluating alternative plutonium disposition technologies to MOX that will achieve a safe and secure solution more quickly and cost effectively. The Administration remains committed to the U.S.-Russia Plutonium Management and Disposition Agreement, and will work with its Russian partners to achieve the goals of the agreement in a mutually beneficial manner.


Earlier, the Department of Energy estimated that construction of the facility would cost about $10 billion and the total cost of the plutonium disposition program via MOX route could reach $34 billion. About $3.9 billion has been spent so far and the facility is reported to be about 60 percent complete. The press quoted Anne Harrington, the deputy administrator for Defense Nuclear Nonproliferation, as saying that

"What we mean by (cold standby) is that we would perform activities associated with protecting the facility and equipment from elements and ensuring they are maintained. ... We will protect the investment should the project be restarted or used for something different."


It is unlikely, however, that the MOX project will resume. The process of evaluating alternative routes could take about 12-18 months.